How Many Dedicated Circuits Does a Commercial Kitchen Need?
By Joseph Myers · November 19, 2026
Request a Quick Quote
Free · No obligation · We respond same day
A Florida electrician explains how to count the dedicated circuits a commercial kitchen needs, what drives the number up, and what a real quote includes.
The honest answer is: one dedicated circuit for nearly every piece of equipment on your line, plus a handful more for the things people forget. In practice, a small cafe might land in the range of eight to twelve dedicated circuits. A full-service kitchen with a hood line, walk-ins, and a dish pit can easily need twenty-five or more. There is no single number that fits every restaurant, because the count comes straight off your equipment schedule, and that is the first thing our crew asks to see.
We wire kitchens from Wellington out to the Space Coast, and the pattern is the same everywhere. Owners budget for the fryers and the hood. They do not budget for the circuits behind them. Counting those circuits early is the difference between a clean inspection and a change order the week before you open.
Why almost everything in a kitchen gets its own circuit
A dedicated circuit means one breaker, one run of wire, one piece of equipment. Nothing else shares it. Commercial kitchen appliances are built for this. The manufacturer's spec sheet for a fryer, a combi oven, or a reach-in cooler will list the voltage, the amperage, and usually a note that it requires its own circuit. The code adopted in Florida backs that up: fixed equipment above a certain load has to be on a circuit sized for it, and any equipment with a motor or heating element that could trip a shared breaker belongs by itself.
The practical reason is simpler. If a dishwasher and a reach-in share a breaker and the breaker trips during a Saturday rush, you lose both. Dedicated circuits keep one failure from taking down the line.
Here is roughly how a typical equipment list breaks out:
- Cooking line: each fryer, griddle, flat top, charbroiler, range, and convection or combi oven gets its own circuit. Gas equipment still needs power for ignition, controls, and blowers, so do not skip it.
- Refrigeration: every walk-in cooler, walk-in freezer, reach-in, undercounter unit, and prep table with a compressor gets a dedicated circuit. Ice machines too.
- Warewashing: the dish machine, the booster heater, and often the garbage disposal each need one.
- Ventilation: the exhaust hood fan, the makeup air unit, and the fire suppression system each get their own.
- Small equipment and counters: the code requires dedicated circuits for countertop receptacles in commercial kitchens too. Toasters, blenders, slicers, panini presses, and espresso machines add up fast. We plan a separate 20-amp circuit for each short section of counter.
- Everything else: POS stations, water heaters, hand sinks with electric tankless units, beverage coolers, and exterior signage.
Count that list honestly and a 60-seat restaurant with a modest line is already past twenty circuits before you touch lighting or HVAC.
What pushes the count, and the cost, higher
The number of circuits is the first driver of cost. The second is what each circuit has to be. A 120-volt, 20-amp circuit for a toaster is a short run of small wire. A 208-volt, three-phase, 50-amp circuit for a combi oven is heavier wire, a bigger breaker, and often a run back to a panel that has to be larger than the one in the building.
Things we see raise the price on a kitchen build-out:
- Panel capacity. Many older buildings along Atlantic Avenue in Delray Beach or in downtown Melbourne came with a panel sized for a retail tenant. A kitchen that needs 25 dedicated circuits may not have 25 open slots, and the service feeding that panel may not have the amperage to support them. A panel or service upgrade turns a wiring job into a utility coordination job.
- Three-phase equipment. Larger ovens, big walk-in compressors, and some dish machines want three-phase power. If the building only has single-phase, you are either changing the service or buying different equipment.
- Distance and access. A hood line against the back wall with the panel at the front of a 4,000 square foot space means long conduit runs. Concrete floors, finished ceilings, and tenant-above situations all slow the crew down.
- GFCI and specialty protection. Florida's adopted code requires GFCI protection on a lot of kitchen receptacles. Those breakers cost more than standard ones, and we see this missed on quotes from contractors who do not do much restaurant work.
- Permit and inspection. Every county we work in, from Palm Beach to Brevard, requires a permit for this work, and a rough-in inspection before walls close. That is a schedule item as much as a cost item.
What a proper quote should include
When you compare bids for kitchen electrical, the cheap one usually left something out. Ask each contractor to show their circuit count tied to your equipment schedule. If the bid does not list circuits by piece of equipment, it is a guess.
A complete quote from our crew covers:
- A load calculation showing the kitchen's demand against the existing service, so you know up front whether a panel or service upgrade is in play.
- A circuit schedule: every dedicated circuit listed with its voltage, amperage, and the equipment it feeds.
- Receptacle types and locations matched to the equipment cord caps, so your installer is not adapting plugs on opening day.
- Permit fees, inspection scheduling, and who pulls the permit.
- A plan for working around your hours if the space is already operating. We do a lot of after-hours and overnight work for restaurants in Boca Raton and Viera that cannot close the dining room.
If a contractor cannot produce that circuit schedule, keep looking. It is the document the inspector will check your work against.
How to get your count right before you sign anything
Start with your equipment list, not the floor plan. Pull the spec sheet for every piece, including the ones you already own and plan to move. Note the voltage and amperage on each. Then add the circuits for counters, ventilation, and warewashing that are not on the equipment list. That gives you a number to hand a contractor, and it keeps the whole bid process honest.
Our restaurant electrical work starts with that list every time, and if you are planning a kitchen anywhere in our commercial service area, we are glad to walk through it with you. Quotes are free and carry no obligation. Call (844) 432-2262 or send your equipment schedule over, and we respond within one business day.
Frequently Asked Questions
Does gas cooking equipment still need a dedicated electrical circuit?
Usually yes. Gas fryers, ranges, and ovens still need power for ignition, controls, and any blower motors, and manufacturers typically call for a dedicated circuit even though the load is small.
Can I add dedicated circuits to an existing kitchen without replacing the panel?
If the panel has open slots and the service has enough capacity for the added load, yes. If either one is maxed out, which is common in older Florida commercial buildings, a panel or service upgrade comes first, and a load calculation will tell you which situation you are in.
Do I need a permit to add circuits in a commercial kitchen in Florida?
Yes. Adding branch circuits in a commercial space requires an electrical permit and inspection in every county we serve, and the health department inspection for the kitchen will expect the electrical permit to be closed out.